Person-hours measure combined labour, while elapsed hours measure time on the clock. A two-person coating task lasting three hours uses six person-hours if both people work throughout.
Updated · NANOLAB Knowledge
The distinction matters for labour costing and site scheduling. Not every task can be accelerated by adding people, and some stages involve waiting or a single available work area. Record the actual staffing pattern rather than multiplying the full project duration by the largest crew size.
Arithmetic example: two people work for three hours, then one person completes a one-hour inspection. Total labour is seven person-hours and elapsed time is four hours if the stages are consecutive.
These figures are illustrative. They do not define a NANOLAB installation schedule or permit shortening product-specific curing and release requirements.
Ask NANOLAB about the exact product and intended use. Use the current product documentation for formulation-specific instructions.